Strategy Implementation¶
Stage 0: Development (Env)¶
Responsibility: 100% Dev lead/TL/Architect
Escalation Point: Dev Lead->PM
Dev lead/TL would be completely responsible for all the issues related to the development environment
Stage 1: QA (Env)¶
Documents: QA Signoff & Test Summary
Responsibility: 100% QA
Escalation point: QA->PM, PM->Dev lead/TL/Architect
Stage 2: UAT (Env)¶
Documents: Sign-off by PM.
Responsibility: 80% QA; 20% BA/PM
QA will be solely responsible for identifying all functionality issues as well as UI/UX issues and requirement gaps.
BA/PM has a shared responsibility in identifying requirement gaps and UI/UX. performance before handing over to the client
Escalation point: PM
Stage 3: Production (Env)¶
Responsibility: 15% client, 35% QA, 25% BA, 25%. PM.
If something goes wrong Production
-
Due to requirement gap- shared between client & BA
-
Missed Happy Path scenarios - QA & PM
-
Missed Edge scenarios - QA & BA
-
Environment and deployment - Dev lead, PM
-
Infrastructure – Architect, TL/Dev-lead
Stage 4: Post-production¶
Documents: RCA & Maintenance log for all bugs, Incident report for critical bags.
QA & Dev lead together to provide RCA
PM to provide Incident report & Maintenance log
Responsibility: 50% QA; 25% dev lead,15%. PM; 10% BA