VI. Post Production

13. Post-Production Support

  • Client raises a critical production issue to the PM.

  • PM, BA and TL gauge the criticality and impact of the issue.

  • The issue could be categorized into either of the following:

    • Feature bug
      • BA negotiates with the client on the criticality of the bug.
      • Top priority issues will be reproduced by the team, fixed in dev env, tested, deployed in staging env retested and then deployed to production.
      • Non-critical issues could be added to the backlog as a future update with the confirmation of the client.
    • Technical, Deployment or high impact issue
      • Dev team fixes the issues in production
      • TL creates an incident report and submits it to the PM and architect.
      • The PM confirms with the client that the issue is fixed and submits the incident report to the client and the delivery head.

postprod1

ISO Document  at stage 12.13

    - Change request
    - Incident report
    - Corrective and Preventive Action
    - Release notes

14. Project Closure

A consolidated project summary will be listed.

PS:

*this doc will be supported by a detailed flowchart

15. Deployment Management

  • The goal of deployment management is to get feature updates into live environments. It may also be involved in deploying components to test or staging environments.

  • The following table shows the different environment switchings, with the requirements to be met for it, along with the approving authorities.